Commercial Tenant Improvement (TI) Permit Drawings: A Step-by-Step Guide
A commercial tenant improvement (TI) project starts with a signed lease and a move-in date, and every week spent in permit review is a week of rent paid on a space that isn't generating revenue yet. TI permit drawings have to move fast without skipping the coordination that keeps them from bouncing back — here's the step-by-step process that keeps both true.
Step 1: Confirm the shell condition and base building rules
Before any design work starts, confirm what the landlord's shell actually provides — stubbed utilities, existing fire sprinkler coverage, ceiling height above the drop ceiling — and pull the base building's rules and regulations, since many landlords impose their own construction standards on top of code requirements. Skipping this step is one of the most common causes of a redesign mid-project.
Step 2: Occupancy classification and existing conditions
The proposed use determines the occupancy classification the permit drawings need to satisfy — a retail space, office, and restaurant fall under different classifications with different egress, plumbing fixture count, and fire-rating requirements. If the classification is changing from the previous tenant's use, that change of occupancy can trigger a more extensive code review than a like-for-like TI would.
Step 3: Coordinated architectural and MEP drawings
TI permit drawings typically include a demolition plan (what's being removed from the previous tenant's build-out), a new floor plan, reflected ceiling plan, and coordinated MEP sheets — mechanical, electrical, and plumbing all need to be drawn against the same architectural background to avoid clashes discovered during construction rather than on paper.
- Demolition plan showing existing conditions to be removed
- New floor plan with partition layout and door schedule
- Reflected ceiling plan coordinating lighting, sprinklers, and HVAC diffusers
- MEP plans cross-referenced against the same architectural floor plan
Step 4: Life safety and accessibility layers
Every commercial TI needs an egress plan showing exit paths and occupant load calculations, plus ADA accessibility compliance for the accessible route, restrooms, and counter heights. These aren't separate submittals — they're layered directly into the same permit drawings and checked by the same plan reviewer.
Step 5: Submit, respond, and track
Once submitted, most jurisdictions return plan check comments in rounds rather than all-or-nothing — responding quickly and completely to each round, rather than partially, is what keeps a TI on a lease-driven timeline. A team that tracks the review status daily and responds within the jurisdiction's turnaround window can often save one to two full review cycles compared to a slower back-and-forth.
A commercial floor plan sheet showing a retail or office tenant improvement layout with partition walls, a door schedule table, and a reflected ceiling plan grid overlay — conveys the coordinated, multi-layer nature of TI permit drawings.
Have a project that touches on this? Our permit drawing services cover architectural, structural, and MEP sets nationwide, or browse the full permitting resource library.
Get Your Permit Drawings Started — Free Estimate
Tell us about your project and we'll tell you exactly what your permit drawings need to include, and a realistic timeline — no obligation.
Get a Free Estimate